rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-stupeniv-1-3
Reconstruction and extension of Poltava Secondary School No. 9 of the Poltava City Council
Poltava Oblast at 3 Shvedska str.
Types of work:
  • engineering and geological surveys
  • engineering and geodetic surveys
  • design documentation of the "P"
  • design documentation of the "R"
Project readiness:
100%
Design year:
2020
Technical and economic indicators
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-vyd-zverhu
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-vyd-z-parkovky
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-dvir
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-perehidna-galereya
Реконструкція з добудовою Полтавської загальноосвітньої школи І-ІІІ ступенів №9
Type of construction reconstruction
Capacity of the facility 480 / 28 students / employees
Plot area 1.6626 ha
Total area 5,182.60 m2
Usable area 4,332.89 m2
Estimated area 4,249.90 m2
Building volume 20,180 m3
Description of the project

The project provides for the reconstruction of the existing educational institution — Poltava Secondary School No. 9 of the Poltava City Council located at 3 Shvedska str.

The reconstruction includes the addition of a separate elementary school building for students of the grades 1 to 4. The forms are completed based on age (same, different age), family features in accordance with the occupancy rates.

The building extension provides for 16 classrooms (4 classrooms for each grade) with recreation areas, classrooms for children with special needs, extended day groups, a library, and a canteen for students. 

The existing building and the extension are connected through the 2nd floor via a glazed passage on supports.

A comprehensive landscaping of the territory is being carried out.

The total number of the students studying in the extension building is 480, the number of employees is 28 teachers.

Work schedule and organization of children’s life at the educational institution are determined by its founder and approved by the educational authorities and territorial bodies of the State Sanitary and Epidemiological Service of Ukraine.

The shelter is currently being designed.

Project solutions

The following project disciplines have been completed:

Project Summary, General Plan, External Water Supply and Sewage Networks, Construction Management Plan, Structural Timberwork, Architectural and Construction Solutions, Production Techniques, Heating, Ventilation and Air Conditioning, Water Supply and Sewage, Heat Supply Mechanical Solutions, Electrical Solutions, Fire Alarm Systems, Communication Systems, Project Financing, Energy Efficiency Arrangements.

The construction will be carried out in one phase.

Design and estimate documentation has been developed for the following buildings and structures, namely:

The 2nd floor passage on supports between the extension and the existing building.

Addition of the elementary school building, consisting of:

  • Lobby with a locker room
  • Staircases
  • Corridors
  • Recreation areas
  • Classrooms
  • Classrooms for children with special needs
  • Auxiliary premises
  • Extended day group classrooms
  • Teachers’ room
  • Library with a reading room and a storeroom
  • Canteen for students
  • Kitchen
  • Storage and pantry
  • Student bathrooms
  • Teacher bathrooms
  • Common bathrooms
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-vyd-zverhu
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-vyd-z-parkovky
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-dvir
rekonstrukciya-z-dobudovoyu-poltavsko-zagalnoosvitno-shkoly-9-perehidna-galereya
Реконструкція з добудовою Полтавської загальноосвітньої школи І-ІІІ ступенів №9